Lecroma — Shaping a resilient future
Demo seed — verify before use. This dashboard distinguishes between declared REZs, proposed or candidate REZs, access-rights projects, planning-portal projects, priority-list projects and offshore wind declared areas. Status does not imply final approval unless confirmed by the relevant authority.
Data currency: 2026-05-18 · 59 of 67 projects verified at confidence ≥ 70/100
Verified URLs span NSW Planning Portal, IPC, DCCEEW EPBC, proponent project sites.
NSW deep diveNew England REZNew England Battery (Solar-linked BESS)

New England Battery (Solar-linked BESS)

ACEN Australia
BESSunder constructionConfidence: Very highCertainty: medium
Capacity and technology
Technology
BESS
Capacity (MW)
1.40 GW
Storage
2.80 GWh
Estimated capex, local spend and peak workforce
Total development cost
~$1.96B benchmark estimate
2800 MWh × $0.7M/MWh (BESS)
Industry benchmark only — not project-specific. Sources: Clean Energy Council, BloombergNEF 2024 Australian utility-scale LCOE inputs, AEMO ISP 2024 cost assumptions. Actual capex varies materially by site, OEM, supply chain and grid-connection works.
Estimated local / regional spend
~$431M benchmark estimate
22% of capex — Clean Energy Council benchmark for renewable energy construction in regional Australia. Actual local content varies by project siting, procurement strategy and any access-scheme local-content conditions.
Estimated peak construction workforce
~1,120 roles benchmark estimate
Industry benchmark: ~0.7 FTE/MW wind, 0.5 FTE/MW solar, 0.4 FTE/MWh BESS, 1.5 FTE/MW pumped hydro. Peak during civil/electrical phase only — operations workforce is typically ~5-10% of construction peak.
Workforce breakdown — sector mix and phasing

Sector mix and phase distribution for the estimated construction workforce. Basis: industry norm (Clean Energy Council, ARENA, AEMO ISP 2024 + comparable EIS Social Impact Assessments). Numbers are decision-support indicators, not a project-specific forecast.

By service sector / industry (peak year)
Civil / earthworks
~168 FTE
Electrical trades
~504 FTE
Mechanical / structural
~168 FTE
Plant operators
~56 FTE
PM / engineering / env
~112 FTE
Logistics / admin
~112 FTE
By phase (across construction window)
PhaseFTEWhat's happening
Mobilisation + civils (year 1)
~672
Site prep, access roads, foundations, early electrical. Civil trades dominant.
Peak construction (year 2)
~1,120
All trades concurrent. Turbine / panel delivery, electrical install, commissioning prep.
Commissioning / demob (year 3)
~784
Specialist electrical and testing. Civil and structural ramping down.
Operations (ongoing)
~78
Permanent O&M workforce — typically 5–10% of construction peak. Plus periodic major-maintenance windows.

Sector mix from CEC, ARENA and AEMO ISP workforce profiles for utility-scale Australian builds. Phase distribution from comparable EIS Social Impact Assessments. Indicative only — actual workforce varies with OEM, contractor strategy, weather and OSOM scheduling.

Approvals and access rights
Project status
under construction
Planning status
Approved March 2020 (SSD-9255); modification approved expanding BESS to 1.4 GW / 2.8 GWh
Access right status
not in REZ access scheme
EPBC status
verify
Grid connection
construction commenced February 2025 (initial 400 MWh phase)
Financial close
post-FID for initial phase
Construction start
2025 (commenced)
Operations start
phased — first phase 2026 (verify)
Location
LGA
Uralla Shire
Region
New England NSW
REZ
New England REZ
REZ relationship
inside declared REZ
Coordinates
-30.65, 151.7 (approximate)
Business certainty
Certainty: mediumScore: 60/100

Approved status (if confirmed) is the strongest single signal — but absent REZ access scheme participation, revenue stack is different from access-right projects.

Planning risk: lowGrid risk: moderateSocial risk: lowWorkforce: lowAccommodation: lowSupply chain: moderateBiodiversity: lowFirst Nations: moderate
Next decision point: Financial close decision
Status timeline
  1. 2026-03-10 · approval
    Planning approval reported by proponent. Verify Planning Portal SSD reference.
Project documents — EIS, SEARs, proponent pages

Direct links to public documents and pages for this project. Phase 2 ingestion will pull updates automatically; Sprint 0 entries are verified manually with a confidence score per record.

Notes

Status updated: under construction (first 400 MWh phase commenced Feb 2025). Co-located with operational 720 MWac New England Solar.

Source confidence: 90/100
Last verified: 2026-05-13
Every material fact on this page is sourced. A "View source" link is provided per source below.
Source evidence
Confidence: Very high
  • primaryNSW Planning Portal — Major Projects
    View source ↗
    Authoritative for NSW SSD and SSI planning status. Hosts each project's Environmental Impact Statement (EIS), SEARs, response to submissions, and other planning documents. Outranks proponent and media reports for planning_status. Per-project EIS and SSD page URLs are tracked under each project's project_documents.
  • secondaryProponent project websites
    View source ↗
    Proponent-supplied content from each project's dedicated page on the proponent's website. Useful for technology, capacity intent, community engagement messaging, project newsletters, fact sheets and timeline updates. Cannot override official planning_status or epbc_status. Per-project page URLs are tracked under each project's project_documents.
  • supportingMedia reporting (context only)
    View source ↗
    Media is used for context, controversy, timing signals and public scrutiny — never as the source of truth for regulatory status.
Open questions
  • Planning status against the NSW Planning Portal — verify SSD reference.
  • EPBC referral status — verify against DCCEEW public notices.
  • Storage MWh and voltage figures — confirm from proponent documents and AEMO Generation Information.
  • Workforce and accommodation commitments — confirm in SSD documentation or VPA.
  • First Nations engagement reporting — confirm in IEP / cultural heritage chapter.
See this project in context