NSW deep diveCentral-West Orana REZBirriwa Battery Energy Storage System

Birriwa Battery Energy Storage System

ACEN Australia
BESSapprovedConfidence: Very high
Capacity and technology
Technology
BESS
Capacity (MW)
600 MW
Storage
1.20 GWh
Estimated capex, local spend and peak workforce
Total development cost
~$840M benchmark estimate
1200 MWh × $0.7M/MWh (BESS)
Industry benchmark only — not project-specific. Sources: Clean Energy Council, BloombergNEF 2024 Australian utility-scale LCOE inputs, AEMO ISP 2024 cost assumptions. Actual capex varies materially by site, OEM, supply chain and grid-connection works.
Estimated local / regional spend
~$185M benchmark estimate
22% of capex — Clean Energy Council benchmark for renewable energy construction in regional Australia. Actual local content varies by project siting, procurement strategy and any access-scheme local-content conditions.
Estimated peak construction workforce
~480 roles benchmark estimate
Industry benchmark: ~0.7 FTE/MW wind, 0.5 FTE/MW solar, 0.4 FTE/MWh BESS, 1.5 FTE/MW pumped hydro. Peak during civil/electrical phase only — operations workforce is typically ~5-10% of construction peak.
Workforce breakdown — sector mix and phasing

Sector mix and phase distribution for the estimated construction workforce. Basis: industry norm (Clean Energy Council, ARENA, AEMO ISP 2024 + comparable EIS Social Impact Assessments). Numbers are decision-support indicators, not a project-specific forecast.

By service sector / industry (peak year)
Civil / earthworks
~72 FTE
Electrical trades
~216 FTE
Mechanical / structural
~72 FTE
Plant operators
~24 FTE
PM / engineering / env
~48 FTE
Logistics / admin
~48 FTE
By phase (across construction window)
PhaseFTEWhat's happening
Mobilisation + civils (year 1)
~288
Site prep, access roads, foundations, early electrical. Civil trades dominant.
Peak construction (year 2)
~480
All trades concurrent. Turbine / panel delivery, electrical install, commissioning prep.
Commissioning / demob (year 3)
~336
Specialist electrical and testing. Civil and structural ramping down.
Operations (ongoing)
~34
Permanent O&M workforce — typically 5–10% of construction peak. Plus periodic major-maintenance windows.

Sector mix from CEC, ARENA and AEMO ISP workforce profiles for utility-scale Australian builds. Phase distribution from comparable EIS Social Impact Assessments. Indicative only — actual workforce varies with OEM, contractor strategy, weather and OSOM scheduling.

Approvals and access rights
Project status
approved
Planning status
Approved by IPC August 2024 as part of Birriwa Solar SSD-29508870
Access right status
awarded — CWO REZ access scheme
EPBC status
verify
Grid connection
in CWO REZ access scheme network design
Financial close
post-approval; not at financial close
Construction start
unknown
Operations start
unknown
Location
LGA
Mid-Western Regional
Region
Central West NSW
REZ
Central-West Orana REZ
REZ relationship
inside declared REZ
Coordinates
-32.3, 149.4 (approximate)
Project documents — EIS, SEARs, proponent pages

Direct links to public documents and pages for this project. Phase 2 ingestion will pull updates automatically; Sprint 0 entries are verified manually with a confidence score per record.

Notes

600 MW for 2 hours = 1200 MWh. Approved as co-located system with Birriwa Solar.

Source confidence: 88/100
Last verified: 2026-05-13
Every material fact on this page is sourced. A "View source" link is provided per source below.
Source evidence
Confidence: Very high
  • primaryNSW Planning Portal — Major Projects
    View source ↗
    Authoritative for NSW SSD and SSI planning status. Hosts each project's Environmental Impact Statement (EIS), SEARs, response to submissions, and other planning documents. Outranks proponent and media reports for planning_status. Per-project EIS and SSD page URLs are tracked under each project's project_documents.
  • primaryEnergyCo NSW
    View source ↗
    Primary authority for NSW Renewable Energy Zones, access schemes, access-right tender outcomes and REZ project coordination under the Electricity Infrastructure Investment Act 2020.
  • primaryAEMO Services / AusEnergy Services
    View source ↗
    Consumer Trustee for NSW LTESA / access-right tenders. Authoritative for access-right award status.
  • secondaryProponent project websites
    View source ↗
    Proponent-supplied content from each project's dedicated page on the proponent's website. Useful for technology, capacity intent, community engagement messaging, project newsletters, fact sheets and timeline updates. Cannot override official planning_status or epbc_status. Per-project page URLs are tracked under each project's project_documents.
Open questions
  • Planning status against the NSW Planning Portal — verify SSD reference.
  • EPBC referral status — verify against DCCEEW public notices.
  • Storage MWh and voltage figures — confirm from proponent documents and AEMO Generation Information.
  • Workforce and accommodation commitments — confirm in SSD documentation or VPA.
  • First Nations engagement reporting — confirm in IEP / cultural heritage chapter.