Wollar Solar Farm
Sector mix and phase distribution for the estimated construction workforce. Basis: industry norm (Clean Energy Council, ARENA, AEMO ISP 2024 + comparable EIS Social Impact Assessments). Numbers are decision-support indicators, not a project-specific forecast.
| Phase | FTE | What's happening |
|---|---|---|
| Mobilisation + civils (year 1) | ~84 | Site prep, access roads, foundations, early electrical. Civil trades dominant. |
| Peak construction (year 2) | ~140 | All trades concurrent. Turbine / panel delivery, electrical install, commissioning prep. |
| Commissioning / demob (year 3) | ~98 | Specialist electrical and testing. Civil and structural ramping down. |
| Operations (ongoing) | ~10 | Permanent O&M workforce — typically 5–10% of construction peak. Plus periodic major-maintenance windows. |
Sector mix from CEC, ARENA and AEMO ISP workforce profiles for utility-scale Australian builds. Phase distribution from comparable EIS Social Impact Assessments. Indicative only — actual workforce varies with OEM, contractor strategy, weather and OSOM scheduling.
Direct links to public documents and pages for this project. Phase 2 ingestion will pull updates automatically; Sprint 0 entries are verified manually with a confidence score per record.
- proponent pageConfidence: Very highWollar Solar Farmhttps://wollarsolar.com.au/ ↗280 MWac solar across ~660,000 panels with single-axis tracking. Construction began early 2023, completion target late 2025.
- otherConfidence: HighWollar BESS — modification applicationhttps://wollarsolar.com.au/bess/ ↗Modification application to expand approved 30 MW / 30 MWh BESS to 280 MW / 560 MWh (2-hour duration).
- planning portal pageConfidence: Very highWollar Solar Farm — NSW Planning Portal (SSD-9254)https://www.planningportal.nsw.gov.au/major-projects/projects/wollar-solar-farm ↗Hosts development consent and modification documents.
Pre-CWO access scheme project, but inside the CWO REZ geographic boundary. Mid-Western Regional LGA. BESS upgrade from 30 MW to 280 MW (~9× expansion) is a significant addition to the CWO REZ storage stack.
Last verified: 2026-05-18
Every material fact on this page is sourced. A "View source" link is provided per source below.
- primaryNSW Planning Portal — Major ProjectsView source ↗Authoritative for NSW SSD and SSI planning status. Hosts each project's Environmental Impact Statement (EIS), SEARs, response to submissions, and other planning documents. Outranks proponent and media reports for planning_status. Per-project EIS and SSD page URLs are tracked under each project's project_documents.
- secondaryProponent project websitesView source ↗Proponent-supplied content from each project's dedicated page on the proponent's website. Useful for technology, capacity intent, community engagement messaging, project newsletters, fact sheets and timeline updates. Cannot override official planning_status or epbc_status. Per-project page URLs are tracked under each project's project_documents.
- Planning status against the NSW Planning Portal — verify SSD reference.
- EPBC referral status — verify against DCCEEW public notices.
- Storage MWh and voltage figures — confirm from proponent documents and AEMO Generation Information.
- Workforce and accommodation commitments — confirm in SSD documentation or VPA.
- First Nations engagement reporting — confirm in IEP / cultural heritage chapter.