Yanco Delta Wind Farm
Sector mix and phase distribution for the estimated construction workforce. Basis: industry norm (Clean Energy Council, ARENA, AEMO ISP 2024 + comparable EIS Social Impact Assessments). Numbers are decision-support indicators, not a project-specific forecast.
| Phase | FTE | What's happening |
|---|---|---|
| Mobilisation + civils (year 1) | ~613 | Site prep, access roads, foundations, early electrical. Civil trades dominant. |
| Peak construction (year 2) | ~1,022 | All trades concurrent. Turbine / panel delivery, electrical install, commissioning prep. |
| Commissioning / demob (year 3) | ~715 | Specialist electrical and testing. Civil and structural ramping down. |
| Operations (ongoing) | ~72 | Permanent O&M workforce — typically 5–10% of construction peak. Plus periodic major-maintenance windows. |
Sector mix from CEC, ARENA and AEMO ISP workforce profiles for utility-scale Australian builds. Phase distribution from comparable EIS Social Impact Assessments. Indicative only — actual workforce varies with OEM, contractor strategy, weather and OSOM scheduling.
Anchor project for SW REZ. Adjacent peer to Vestas-served projects but no Vestas commercial role here (Goldwind OEM, Origin client). Deliverability turns on planning and shared logistics with other SW REZ projects.
- 2026-04-22 · access right awardedAccess rights confirmed under the SW REZ access scheme.
Direct links to public documents and pages for this project. Phase 2 ingestion will pull updates automatically; Sprint 0 entries are verified manually with a confidence score per record.
- planning portal pageConfidence: Very highYanco Delta Wind Farm — NSW Planning Portalhttps://www.planningportal.nsw.gov.au/major-projects/projects/yanco-delta-wind-farm ↗Hosts EIS, response to submissions, approval documents.
- proponent pageConfidence: Very highYanco Delta Wind Farm Project (dedicated site)https://yancodelta.com.au/ ↗Project-specific website.
- media releaseConfidence: Very highPublished: 2024-04-12Origin acquires 1.5 GW Yanco Delta Wind development in NSWhttps://www.originenergy.com.au/about/investors-media/origin-acquires-1-5-gw-yanco-delta-wind-development-in-nsw/ ↗Origin acquisition announcement, April 2024.
- media releaseConfidence: Very highOrigin secures transmission access for Yanco Deltahttps://www.originenergy.com.au/about/investors-media/origin-secures-transmission-access-for-yanco-delta/ ↗Origin transmission access announcement.
Capacity updated: up to 1.5 GW wind + 800 MWh BESS. NSW approval Dec 2023; EPBC Feb 2024; Origin acquired April 2024. Up to 210 wind turbines on 33,000 ha site. ~10 km NW of Jerilderie. SW REZ access right: 1,460 MW (binding award). Proponent originally floated ~1,500 MW total ambition; the access-right scale is the contractual entitlement.
Last verified: 2026-05-18
Every material fact on this page is sourced. A "View source" link is provided per source below.
- primaryNSW Planning Portal — Major ProjectsView source ↗Authoritative for NSW SSD and SSI planning status. Hosts each project's Environmental Impact Statement (EIS), SEARs, response to submissions, and other planning documents. Outranks proponent and media reports for planning_status. Per-project EIS and SSD page URLs are tracked under each project's project_documents.
- primaryDCCEEW — EPBC referrals and approvalsView source ↗Authoritative for EPBC referral and approval status. EPBC approval is separate from state planning approval.
- primaryEnergyCo NSWView source ↗Primary authority for NSW Renewable Energy Zones, access schemes, access-right tender outcomes and REZ project coordination under the Electricity Infrastructure Investment Act 2020.
- primaryAEMO Services / AusEnergy ServicesView source ↗Consumer Trustee for NSW LTESA / access-right tenders. Authoritative for access-right award status.
- secondaryProponent project websitesView source ↗Proponent-supplied content from each project's dedicated page on the proponent's website. Useful for technology, capacity intent, community engagement messaging, project newsletters, fact sheets and timeline updates. Cannot override official planning_status or epbc_status. Per-project page URLs are tracked under each project's project_documents.
- Planning status against the NSW Planning Portal — verify SSD reference.
- EPBC referral status — verify against DCCEEW public notices.
- Storage MWh and voltage figures — confirm from proponent documents and AEMO Generation Information.
- Workforce and accommodation commitments — confirm in SSD documentation or VPA.
- First Nations engagement reporting — confirm in IEP / cultural heritage chapter.