NSW deep diveSouth West REZ

South West REZ

EnergyCo NSW · Riverina; Murrumbidgee, Edward River, Federation, Berrigan LGAs
declaredConfidence: Very high

Riverina REZ. Access rights awarded to six projects across four proponents totalling ~3.56 GW. Coordination with PEC Eastern Section operating infrastructure.

Legal/policy basis: Declared under the Electricity Infrastructure Investment Act 2020 (NSW). Closest REZ to Project EnergyConnect.
20
Projects tracked
13.62 GW
Capacity tracked
0
Access rights awarded
3
Investigation / early
Map preview
South West
Cumulative pressure — Multiple (Murrumbidgee, Edward River, Federation, Berrigan, Hay Shire)
OSOM: highRoads: highRentals: moderateWater: moderateHealth: moderateWaste: moderate

6 access-right projects across four proponents totalling ~3.56 GW initial access (~5 GW full development). Pottinger alone is approved for up to 1.3 GW with ~900 peak construction roles. Yanco Delta is approved at 1.5 GW. Dinawan Energy Hub aggregates three points-of-connection in a small geographic footprint. Logistics interface with PEC Eastern Section operating infrastructure. Indicative construction workforce sum across approved SW REZ projects exceeds 2,000 roles; overlapping windows from 2027.

Mitigation: PEC NSW Eastern Section now operating reduces some delivery risk. Project-level workforce strategies expected. Coordination opportunities around shared logistics, port-to-site routes and rail aggregates from Victoria (Deniliquin via the Echuca-Deniliquin line) are not yet formalised at REZ level.

Project pipeline (20)
ProjectProponentTechnologyCapacityLGAStatusConfidence
Bullawah Wind FarmBayWa r.e.wind262.3 MWHay Shire / Murrumbidgee / Edward RiverEIS preparationConfidence: High
Pottinger Energy ParkSomeva Renewables / AGL Energy Hubs (JV)wind831.2 MWMurrumbidgee / FederationapprovedConfidence: Very high
Yanco Delta Wind FarmOrigin Energywind1.46 GWFederation CouncilapprovedConfidence: Very high
Dinawan Energy Hub — Wind Farm (POC 1+2)Spark Renewableswind707 MWMurrumbidgeeresponse to submissionsConfidence: Very high
Dinawan Energy Hub — Solar Farm + BESS (POC 3)Spark Renewablessolar300 MWMurrumbidgeeapprovedConfidence: Very high
Conargo Wind FarmSquadron Energywind168 MWEdward River / MurrumbidgeescopingConfidence: High
Argoon Wind FarmRES Australiawind901 MWMurrumbidgeescopingConfidence: High
Tchelery Wind FarmNeoen Australiawind577 MWEdward RiverscopingConfidence: High
Wanganella Wind FarmEquiswind840 MWEdward RiverEIS preparationConfidence: High
Coleambally Solar FarmNeoen Australiasolar189 MWMurrumbidgeeoperatingConfidence: Very high
Riverina Solar Farm (Darlington Point)Edify Energysolar333 MWMurrumbidgeeoperatingConfidence: High
Berrigan Wind Farm (withdrawn)Windlab (Tattarang / Andrew Forrest)windunknownBerriganwithdrawnConfidence: Medium
Abercrombie Wind FarmVestas (Abercrombie Windfarm Pty Ltd)wind2.50 GWHay ShireEIS preparationConfidence: High
Baldon Wind FarmGoldwind Australiawind1.40 GWMurray River / Edward Riverresponse to submissionsConfidence: High
Saltbush Wind FarmOctopus Investments Australiawind400 MWEdward RiverEIS preparationConfidence: High
Junction Rivers Wind FarmWindlab (Tattarang / Andrew Forrest, via Squadron Energy)wind750 MWBalranald ShireEIS preparationConfidence: High
Koorakee Energy ParkSquadron Energyhybrid2.00 GWBalranald ShireEIS preparationConfidence: High
Gol Gol Wind FarmSquadron EnergywindunknownWentworth ShireEIS preparationConfidence: High
Gol Gol Solar FarmSquadron EnergysolarunknownWentworth ShireEIS preparationConfidence: Medium
Gol Gol Battery (BESS)Squadron EnergyBESSunknownWentworth ShireEIS preparationConfidence: Medium
Shared value commitments tracked for this REZ
voluntary planning agreementannounced

Voluntary Planning Agreements expected as projects move from access rights to SSD assessment. Demo seed — verify per project.

Beneficiary: Host LGA(s) · Governance: Council-administered
community benefit fundannounced

Community benefit fund of the form typical for projects of this scale (proponent-supplied figures pending verification on Planning Portal SSD documents).

Beneficiary: Federation Council and Jerilderie / Berrigan communities · Governance: Proponent-administered with council oversight
Open full shared value ledger →
Workforce demand vs regional supply

ABS Census 2021 baseline aggregated across host LGAs; peak demand from project workforce benchmarks.

fundamental gap453% of baseline
Total employed (host LGAs)
17,100
ABS Census 2021
Construction baseline
~1,335 FTE
applied construction industry share
Peak demand (2030)
~6,053 FTE
REZ projects only (excl. competing sectors)
Full workforce module + skills pipeline →
Upcoming decisions in this REZ (2)
  • 2027-02eis exhibition openArgoon Wind Farm — EIS submission to DPHI expected

    Following scoping report, EIS submission for the 901 MW + 2,300 MWh project (RES / Aula Energy) expected Q1 2027. Largest SW REZ candidate not yet awarded access rights.

  • 2027-06access scheme announcementSW REZ access scheme — possible expansion round

    Indicative — industry expects an SW REZ access-right expansion round given 15+ GW of unsuccessful bids in the 2024 round. Would unlock candidate projects (Argoon, Wanganella, Tchelery, Conargo).

Full decision points calendar →