NSW deep diveSouth West REZRiverina Solar Farm (Darlington Point)

Riverina Solar Farm (Darlington Point)

Edify Energy
solaroperatingConfidence: High
Capacity and technology
Technology
solar
Capacity (MW)
333 MW
Estimated capex, local spend and peak workforce
Total development cost
~$400M benchmark estimate
333 MW × $1.2M/MW (solar)
Industry benchmark only — not project-specific. Sources: Clean Energy Council, BloombergNEF 2024 Australian utility-scale LCOE inputs, AEMO ISP 2024 cost assumptions. Actual capex varies materially by site, OEM, supply chain and grid-connection works.
Estimated local / regional spend
~$88M benchmark estimate
22% of capex — Clean Energy Council benchmark for renewable energy construction in regional Australia. Actual local content varies by project siting, procurement strategy and any access-scheme local-content conditions.
Estimated peak construction workforce
~167 roles benchmark estimate
Industry benchmark: ~0.7 FTE/MW wind, 0.5 FTE/MW solar, 0.4 FTE/MWh BESS, 1.5 FTE/MW pumped hydro. Peak during civil/electrical phase only — operations workforce is typically ~5-10% of construction peak.
Workforce breakdown — sector mix and phasing

Sector mix and phase distribution for the estimated construction workforce. Basis: industry norm (Clean Energy Council, ARENA, AEMO ISP 2024 + comparable EIS Social Impact Assessments). Numbers are decision-support indicators, not a project-specific forecast.

By service sector / industry (peak year)
Civil / earthworks
~42 FTE
Electrical trades
~50 FTE
Mechanical / structural
~17 FTE
Plant operators
~17 FTE
PM / engineering / env
~17 FTE
Logistics / admin
~25 FTE
By phase (across construction window)
PhaseFTEWhat's happening
Mobilisation + civils (year 1)
~100
Site prep, access roads, foundations, early electrical. Civil trades dominant.
Peak construction (year 2)
~167
All trades concurrent. Turbine / panel delivery, electrical install, commissioning prep.
Commissioning / demob (year 3)
~117
Specialist electrical and testing. Civil and structural ramping down.
Operations (ongoing)
~12
Permanent O&M workforce — typically 5–10% of construction peak. Plus periodic major-maintenance windows.

Sector mix from CEC, ARENA and AEMO ISP workforce profiles for utility-scale Australian builds. Phase distribution from comparable EIS Social Impact Assessments. Indicative only — actual workforce varies with OEM, contractor strategy, weather and OSOM scheduling.

Approvals and access rights
Project status
operating
Planning status
Approved (SSD-7482); operating
Access right status
not in SW REZ access scheme — pre-dates the scheme
EPBC status
verify
Grid connection
operating; connected to Transgrid network
Financial close
post-FID; operating
Construction start
unknown
Operations start
operating
Location
LGA
Murrumbidgee
Region
Riverina NSW
REZ
South West REZ
REZ relationship
inside declared REZ
Coordinates
-34.57, 146 (approximate)
Project documents — EIS, SEARs, proponent pages

Direct links to public documents and pages for this project. Phase 2 ingestion will pull updates automatically; Sprint 0 entries are verified manually with a confidence score per record.

Notes

Operating solar at Darlington Point. Capacity figure indicative — verify against AEMO Generation Information. Pre-dates SW REZ access scheme. Operating asset, not a candidate for access scheme expansion.

Source confidence: 82/100
Last verified: 2026-05-13
Every material fact on this page is sourced. A "View source" link is provided per source below.
Source evidence
Confidence: High
  • primaryNSW Planning Portal — Major Projects
    View source ↗
    Authoritative for NSW SSD and SSI planning status. Hosts each project's Environmental Impact Statement (EIS), SEARs, response to submissions, and other planning documents. Outranks proponent and media reports for planning_status. Per-project EIS and SSD page URLs are tracked under each project's project_documents.
  • primaryAEMO — Generation Information
    View source ↗
    Technical pipeline data for NEM connections. Authoritative for grid-connection technical status.
  • secondaryProponent project websites
    View source ↗
    Proponent-supplied content from each project's dedicated page on the proponent's website. Useful for technology, capacity intent, community engagement messaging, project newsletters, fact sheets and timeline updates. Cannot override official planning_status or epbc_status. Per-project page URLs are tracked under each project's project_documents.
Open questions
  • Planning status against the NSW Planning Portal — verify SSD reference.
  • EPBC referral status — verify against DCCEEW public notices.
  • Storage MWh and voltage figures — confirm from proponent documents and AEMO Generation Information.
  • Workforce and accommodation commitments — confirm in SSD documentation or VPA.
  • First Nations engagement reporting — confirm in IEP / cultural heritage chapter.