Lecroma — Shaping a resilient future
Demo seed — verify before use. This dashboard distinguishes between declared REZs, proposed or candidate REZs, access-rights projects, planning-portal projects, priority-list projects and offshore wind declared areas. Status does not imply final approval unless confirmed by the relevant authority.
Data currency: 2026-05-18 · 59 of 67 projects verified at confidence ≥ 70/100
Verified URLs span NSW Planning Portal, IPC, DCCEEW EPBC, proponent project sites.
NSW deep diveSouth West REZSaltbush Wind Farm

Saltbush Wind Farm

Octopus Investments Australia
windEIS preparationConfidence: High
Capacity and technology
Technology
wind
Capacity (MW)
400 MW
Storage
1.20 GWh
Estimated capex, local spend and peak workforce
Total development cost
~$2.24B benchmark estimate
400 MW × $3.5M/MW (wind, NSW 2025-26 escalated) + + 1200 MWh × $0.7M/MWh (co-located BESS)
Industry benchmark only — not project-specific. Sources: Clean Energy Council, BloombergNEF 2024 Australian utility-scale LCOE inputs, AEMO ISP 2024 cost assumptions. Actual capex varies materially by site, OEM, supply chain and grid-connection works.
Estimated local / regional spend
~$493M benchmark estimate
22% of capex — Clean Energy Council benchmark for renewable energy construction in regional Australia. Actual local content varies by project siting, procurement strategy and any access-scheme local-content conditions.
Estimated peak construction workforce
~280 roles benchmark estimate
Industry benchmark: ~0.7 FTE/MW wind, 0.5 FTE/MW solar, 0.4 FTE/MWh BESS, 1.5 FTE/MW pumped hydro. Peak during civil/electrical phase only — operations workforce is typically ~5-10% of construction peak.
Workforce breakdown — sector mix and phasing

Sector mix and phase distribution for the estimated construction workforce. Basis: industry norm (Clean Energy Council, ARENA, AEMO ISP 2024 + comparable EIS Social Impact Assessments). Numbers are decision-support indicators, not a project-specific forecast.

By service sector / industry (peak year)
Civil / earthworks
~84 FTE
Electrical trades
~50 FTE
Mechanical / structural
~62 FTE
Plant operators
~34 FTE
PM / engineering / env
~28 FTE
Logistics / admin
~22 FTE
By phase (across construction window)
PhaseFTEWhat's happening
Mobilisation + civils (year 1)
~168
Site prep, access roads, foundations, early electrical. Civil trades dominant.
Peak construction (year 2)
~280
All trades concurrent. Turbine / panel delivery, electrical install, commissioning prep.
Commissioning / demob (year 3)
~196
Specialist electrical and testing. Civil and structural ramping down.
Operations (ongoing)
~20
Permanent O&M workforce — typically 5–10% of construction peak. Plus periodic major-maintenance windows.

Sector mix from CEC, ARENA and AEMO ISP workforce profiles for utility-scale Australian builds. Phase distribution from comparable EIS Social Impact Assessments. Indicative only — actual workforce varies with OEM, contractor strategy, weather and OSOM scheduling.

Approvals and access rights
Project status
EIS preparation
Planning status
SEARs issued; EIS in preparation; project lodged on NSW Major Projects portal as Booroorban (Saltbush) Wind Farm
Access right status
not awarded in 2024 SW REZ access round
EPBC status
verify on EPBC public portal
Grid connection
grid-connection options under assessment
Financial close
subject to determination
Construction start
2028
Operations start
2030
Location
LGA
Edward River
Region
Riverina NSW — Booroorban (north of Deniliquin)
REZ
South West REZ
REZ relationship
inside declared REZ
Coordinates
-34.93, 145.13 (approximate)
Project documents — EIS, SEARs, proponent pages

Direct links to public documents and pages for this project. Phase 2 ingestion will pull updates automatically; Sprint 0 entries are verified manually with a confidence score per record.

Notes

Octopus Investments Australia development. Co-located solar farm referenced on proponent site (capacity unspecified). Powering ~173,000 homes per Octopus. Inside Edward River Council area.

Source confidence: 78/100
Last verified: 2026-05-18
Every material fact on this page is sourced. A "View source" link is provided per source below.
Source evidence
Confidence: High
  • primaryNSW Planning Portal — Major Projects
    View source ↗
    Authoritative for NSW SSD and SSI planning status. Hosts each project's Environmental Impact Statement (EIS), SEARs, response to submissions, and other planning documents. Outranks proponent and media reports for planning_status. Per-project EIS and SSD page URLs are tracked under each project's project_documents.
  • secondaryProponent project websites
    View source ↗
    Proponent-supplied content from each project's dedicated page on the proponent's website. Useful for technology, capacity intent, community engagement messaging, project newsletters, fact sheets and timeline updates. Cannot override official planning_status or epbc_status. Per-project page URLs are tracked under each project's project_documents.
Open questions
  • Planning status against the NSW Planning Portal — verify SSD reference.
  • EPBC referral status — verify against DCCEEW public notices.
  • Storage MWh and voltage figures — confirm from proponent documents and AEMO Generation Information.
  • Workforce and accommodation commitments — confirm in SSD documentation or VPA.
  • First Nations engagement reporting — confirm in IEP / cultural heritage chapter.