Oven Mountain Pumped Hydro Energy Storage
Sector mix and phase distribution for the estimated construction workforce. Basis: industry norm (Clean Energy Council, ARENA, AEMO ISP 2024 + comparable EIS Social Impact Assessments). Numbers are decision-support indicators, not a project-specific forecast.
| Phase | FTE | What's happening |
|---|---|---|
| Mobilisation + civils (year 1) | ~810 | Site prep, access roads, foundations, early electrical. Civil trades dominant. |
| Peak construction (year 2) | ~1,350 | All trades concurrent. Turbine / panel delivery, electrical install, commissioning prep. |
| Commissioning / demob (year 3) | ~945 | Specialist electrical and testing. Civil and structural ramping down. |
| Operations (ongoing) | ~95 | Permanent O&M workforce — typically 5–10% of construction peak. Plus periodic major-maintenance windows. |
Sector mix from CEC, ARENA and AEMO ISP workforce profiles for utility-scale Australian builds. Phase distribution from comparable EIS Social Impact Assessments. Indicative only — actual workforce varies with OEM, contractor strategy, weather and OSOM scheduling.
Direct links to public documents and pages for this project. Phase 2 ingestion will pull updates automatically; Sprint 0 entries are verified manually with a confidence score per record.
- planning portal pageConfidence: Very highOven Mountain Pumped Hydro Energy Storage — NSW Planning Portalhttps://www.planningportal.nsw.gov.au/major-projects/projects/oven-mountain-pumped-hydro-energy-storage ↗EIS exhibition notice issued.
- proponent pageConfidence: Very highOven Mountain Pumped Hydro Project — proponent sitehttps://www.ompshydro.com.au/ ↗900 MW / 7,200 MWh (8-hour). Off-river. Two reservoirs + tunnels + underground power station with 600 m head.
- otherConfidence: HighOven Mountain PHES — Kempsey Shire Council pagehttps://www.kempsey.nsw.gov.au/Your-Valley/Ongoing-works-in-the-shire/Oven-Mountain-Pumped-Hydro-Energy-Storage-project ↗Council community engagement page.
900 MW / 7,200 MWh off-river pumped hydro. Two reservoirs + tunnels + underground power station with 600 m elevation difference. Located near the Macleay River between Armidale and Kempsey. Alinta Energy is developer. Targets 2026 construction subject to state and Commonwealth approvals.
Last verified: 2026-05-13
Every material fact on this page is sourced. A "View source" link is provided per source below.
- primaryNSW Planning Portal — Major ProjectsView source ↗Authoritative for NSW SSD and SSI planning status. Hosts each project's Environmental Impact Statement (EIS), SEARs, response to submissions, and other planning documents. Outranks proponent and media reports for planning_status. Per-project EIS and SSD page URLs are tracked under each project's project_documents.
- secondaryProponent project websitesView source ↗Proponent-supplied content from each project's dedicated page on the proponent's website. Useful for technology, capacity intent, community engagement messaging, project newsletters, fact sheets and timeline updates. Cannot override official planning_status or epbc_status. Per-project page URLs are tracked under each project's project_documents.
- secondaryCouncil minutes — CWO REZ LGAsView source ↗Council minutes, agendas, planning decisions affecting REZ delivery.
- Planning status against the NSW Planning Portal — verify SSD reference.
- EPBC referral status — verify against DCCEEW public notices.
- Storage MWh and voltage figures — confirm from proponent documents and AEMO Generation Information.
- Workforce and accommodation commitments — confirm in SSD documentation or VPA.
- First Nations engagement reporting — confirm in IEP / cultural heritage chapter.