Thunderbolt Wind Farm
Sector mix and phase distribution for the estimated construction workforce. Basis: industry norm (Clean Energy Council, ARENA, AEMO ISP 2024 + comparable EIS Social Impact Assessments). Numbers are decision-support indicators, not a project-specific forecast.
| Phase | FTE | What's happening |
|---|---|---|
| Mobilisation + civils (year 1) | ~80 | Site prep, access roads, foundations, early electrical. Civil trades dominant. |
| Peak construction (year 2) | ~134 | All trades concurrent. Turbine / panel delivery, electrical install, commissioning prep. |
| Commissioning / demob (year 3) | ~94 | Specialist electrical and testing. Civil and structural ramping down. |
| Operations (ongoing) | ~9 | Permanent O&M workforce — typically 5–10% of construction peak. Plus periodic major-maintenance windows. |
Sector mix from CEC, ARENA and AEMO ISP workforce profiles for utility-scale Australian builds. Phase distribution from comparable EIS Social Impact Assessments. Indicative only — actual workforce varies with OEM, contractor strategy, weather and OSOM scheduling.
Direct links to public documents and pages for this project. Phase 2 ingestion will pull updates automatically; Sprint 0 entries are verified manually with a confidence score per record.
- proponent pageConfidence: Very highThunderbolt Energy Hub — Neoen Australiahttps://thunderboltwindfarm.com.au/ ↗Up to 32 wind turbines, ~6-7 MW each (~192 MW total). Between Bendemeer and Kentucky, ~47 km NE of Tamworth.
- approval instrumentConfidence: Very highPublished: 2024-05-08Thunderbolt Wind Farm — IPC determination (8 May 2024)https://www.ipcn.nsw.gov.au/news/2024/05/thunderbolt-wind-farm ↗NSW Independent Planning Commission approval subject to conditions.
First NE REZ wind farm IPC-approved at this scale. Two-LGA project. Spans Tamworth and Uralla council areas. Construction date dependent on Neoen post-approval engineering and grid-connection sequencing.
Last verified: 2026-05-15
Every material fact on this page is sourced. A "View source" link is provided per source below.
- primaryNSW Planning Portal — Major ProjectsView source ↗Authoritative for NSW SSD and SSI planning status. Hosts each project's Environmental Impact Statement (EIS), SEARs, response to submissions, and other planning documents. Outranks proponent and media reports for planning_status. Per-project EIS and SSD page URLs are tracked under each project's project_documents.
- secondaryProponent project websitesView source ↗Proponent-supplied content from each project's dedicated page on the proponent's website. Useful for technology, capacity intent, community engagement messaging, project newsletters, fact sheets and timeline updates. Cannot override official planning_status or epbc_status. Per-project page URLs are tracked under each project's project_documents.
- Planning status against the NSW Planning Portal — verify SSD reference.
- EPBC referral status — verify against DCCEEW public notices.
- Storage MWh and voltage figures — confirm from proponent documents and AEMO Generation Information.
- Workforce and accommodation commitments — confirm in SSD documentation or VPA.
- First Nations engagement reporting — confirm in IEP / cultural heritage chapter.